MLP Ventures Plymouth Township Data Center (former Cleveland-Cliffs Conshohocken plant)

Conshohocken · Pennsylvania · Montgomery   Proposed

Project timeline

  1. · Scheduled

    Zoning hearing on 900 Conshohocken Road

    Plymouth Township lists a livestream for the hearing on the proposed data center. The township’s project page has the application and recordings of earlier hearings.

    Official source · Watch the township livestream

  2. · Cancelled

    Township cancels September hearing

    The township cancelled this hearing date. The application remained under review.

    Official source

  3. · Milestone

    Zoning board hears the application

    The township published a recording of the hearing on the proposed data center.

    Official source

  4. · Milestone

    Applicant seeks a zoning exception

    The township posted the applicant’s request to reuse buildings at 900 Conshohocken Road as a data center.

    Official source

Project details

The applicant is seeking a zoning exception to redevelop the former steel mill at 900 Conshohocken Road as a data center. Plymouth Township publishes the application, hearing notices and recordings.

Reported address
900 Conshohocken Road
Operator or developer
MLP Ventures
Cooling
Closed-loop cooling
Reported land area
66 acres reported
Reported investment
$9,000,000,000 announced
Permanent jobs
110 permanent jobs reported
Announcement date
2025

Some figures come from the November 2026 U.S. Data Center Registry snapshot and have not been independently checked by this site. Details shown are those found in the linked sources. Other information may not be public or may still need research.

Sources

Registry snapshot November 5, 2026.