MLP Ventures Plymouth Township Data Center (former Cleveland-Cliffs Conshohocken plant)
Conshohocken · Pennsylvania · Montgomery Proposed
Project timeline
Zoning hearing on 900 Conshohocken Road
Plymouth Township lists a livestream for the hearing on the proposed data center. The township’s project page has the application and recordings of earlier hearings.
Township cancels September hearing
The township cancelled this hearing date. The application remained under review.
Zoning board hears the application
The township published a recording of the hearing on the proposed data center.
Applicant seeks a zoning exception
The township posted the applicant’s request to reuse buildings at 900 Conshohocken Road as a data center.
Project details
The applicant is seeking a zoning exception to redevelop the former steel mill at 900 Conshohocken Road as a data center. Plymouth Township publishes the application, hearing notices and recordings.
- Reported address
- 900 Conshohocken Road
- Operator or developer
- MLP Ventures
- Cooling
- Closed-loop cooling
- Reported land area
- 66 acres reported
- Reported investment
- $9,000,000,000 announced
- Permanent jobs
- 110 permanent jobs reported
- Announcement date
- 2025
Some figures come from the November 2026 U.S. Data Center Registry snapshot and have not been independently checked by this site. Details shown are those found in the linked sources. Other information may not be public or may still need research.
Sources
Registry snapshot November 5, 2026.
Location
Approximate area.
Show on map