  1. · Milestone

    Commissioners adopt land-use rules

    The board approved the code changes. The rules set a 50 kW limit on IT power and require Limited Impact Special Review.

    Official source

  2. · Milestone

    Planning Commission holds public hearing

    The commission held a public hearing on proposed land-use rules for data centers in unincorporated Boulder County.

    Official source

  3. · Milestone

    County starts reviewing data center rules

    Commissioners authorized a code review and temporarily paused applications.

    Official source

What changed

On November 10 the Board of County Commissioners approved land-use code amendments covering data centers, including a 50 kW IT energy cutoff.